The project Location is Al Qutaina 1 – Phase One, Sharjah. The
client is Sharjah Electricity, Water and Gas Authority (SEWA), via the
Electricity Distribution Department. The objective is to improve and expand the
electrical network; ensure energy stability.
Engineer Ahmed Albas, Deputy Director of Electricity
Distribution Department, stated that currently 6 substations have been
installed and connected with each other. The14 distribution panels have been
installed. More than 29 kilometers of electrical cables have been laid.
![]() |
Image is Used for Illustrative Purpose Only. Image Courtesy is WAM |
0 Comments