The Project location is in Sohar, Sultanate of Oman. The Owner/Operator
is ENGIE STOMO (SUEZ TRACTEBEL OPERATION & MAINTENANCE OMAN L.L.C.). The Power
Generation capacity is 585 MW Combined Cycle Gas Turbine (CCGT). Desalination
Capacity is 150,000 m³/day using Multi-Stage Flash (MSF) technology. Recommissioned
Capacity is 405 MW Open Cycle Gas Turbine (OCGT) as per new operational mode. Switch
from CCGT to OCGT will Mark a strategic shift in operations.
Original PPA Expiry was May 2022. New PPA Signed was in October
2024. The Commercial Operation Date (COD) was March 28, 2025. This project will
add 405 MW critical capacity to Oman’s electricity grid. To supports national power
security, this will reinforce Oman's commitment to diversified energy. This will
enhance sustainability through lifecycle extension by utilizing the existing assets.
The OCGT less efficient than CCGT but quicker to deploy in emergencies or peak
demand.