Nesma Infrastructure Secures $66.6M Contract for Abqaiq Substation Replacement

Introduction

Nesma Infrastructure & Technology has signed a big contract with Saudi Energy. The purpose of this project is to replace Abqaiq Substation 49 in eastern region. This project will strengthen Saudi Arabia's energy sector. It will also support electricity need in this area.

Nesma Infrastructure Secures $66.6M Contract for Abqaiq Substation Replacement

Key Project Details

Feature Details
ClientSaudi Energy
ContractorNesma Infrastructure and Technology
LocationAbqaiq, Eastern Region, Saudi Arabia
Substation Type230/69 KV
Timeframe25 months

Impact of This Project

  • Better Reliability and Stability: The major risk of tripping and voltage up & down will be low. The substation will be more stable with this new technology. It will fullfill the electricity demand of households and industry.
  • Industrial Growth: There are many oil and gas facilities in Abqaiq area. These industries will get continues electricity supply with upgradation of this project.
  • Local Jobs: This $66.6 million dollar project will bring more jobs and employments in engineering, labor, and supply chain sector.

More Information

The scope of work include replacement of old substation with new and modern technology substation. The capacity and efficiency of substation will increase by doing this. The main goal is to supply stable electricity in region. This project shows that Nesma Infrastructure and Technology has big role in Saudi Vision 2030.